How do I build the officials game schedule?

Anyone who can open Assign Officials can build the schedule, including the assignor. You don't need the event director to load it first. Open Go to Assign Officials on the Officials tab and choose Start building your schedule to make the grid by hand, or Already have a spreadsheet? Import it instead to upload your game schedule. Build each day and each complex, then click Save assignments.

Where:

Events → Officials tab → Go to Assign Officials.

Option 1: Build it by hand

  1. Click Start building your schedule.
  2. Pick the Location (complex).
  3. Click the day tab you're building.
  4. Fill in Start time, End time, Minutes per game (start to start, so a 45-minute game with a 15-minute break is 60), Number of fields, and First field # (if the complex's fields are 6 to 11, enter 6 fields starting at 6).
  5. Click Generate schedule. You get one row per game time, with a column for each field.
  6. Repeat for every other day, and for every other complex on each day. Each complex and day is built separately. A complex you skip has no games.

Option 2: Import a spreadsheet

  1. Click Already have a spreadsheet? Import it instead.
  2. Drag in a CSV or Excel file, or use Paste from clipboard. Download template gives you the columns. Date, Start Time and Field/Court are required. Complex, Home Team, Away Team, Division/Age, Game Length, # of Officials Needed and Game ID are optional.
  3. Check the column matches on Confirm column mapping, then review Preview & confirm.
  4. Choose Replace (overwrite those dates and complexes) or Merge (add new times and fields, keep existing assignments), then click Generate games.

If your games are in another scheduling system, export them as a spreadsheet and import it. That way the officials schedule has exactly the same games.

Then

Assign officials to the games (see O-05) and click Save assignments. Nothing is stored until you save. When it looks right, send it from the Officials tab (see O-07).

Good to know

  • Clicking Generate schedule again for a day and complex you've already built replaces that grid, including its assignments. If game times change after you've assigned officials, change them instead (see O-11). Officials stay on their games.
  • Use ← Switch how you're building this to go back and choose the other option.
  • The complexes in the Location list come from the event. If one is missing, add it on Edit Event first.
  • Only games that have at least one official assigned count as games for officials. An empty time and field slot isn't a game.