Option 1: Build it by hand
- Click Start building your schedule.
- Pick the Location (complex).
- Click the day tab you're building.
- Fill in Start time, End time, Minutes per game (start to start, so a 45-minute game with a 15-minute break is 60), Number of fields, and First field # (if the complex's fields are 6 to 11, enter 6 fields starting at 6).
- Click Generate schedule. You get one row per game time, with a column for each field.
- Repeat for every other day, and for every other complex on each day. Each complex and day is built separately. A complex you skip has no games.
Option 2: Import a spreadsheet
- Click Already have a spreadsheet? Import it instead.
- Drag in a CSV or Excel file, or use Paste from clipboard. Download template gives you the columns. Date, Start Time and Field/Court are required. Complex, Home Team, Away Team, Division/Age, Game Length, # of Officials Needed and Game ID are optional.
- Check the column matches on Confirm column mapping, then review Preview & confirm.
- Choose Replace (overwrite those dates and complexes) or Merge (add new times and fields, keep existing assignments), then click Generate games.
If your games are in another scheduling system, export them as a spreadsheet and import it. That way the officials schedule has exactly the same games.
Then
Assign officials to the games (see O-05) and click Save assignments. Nothing is stored until you save. When it looks right, send it from the Officials tab (see O-07).